Most plants have been through a “5S clean-up”: a big tidy, colourful tape, photos for a presentation. Three months later the shop floor looks like it did before. The reason is almost always the same: nobody checks the standard in a repeatable way. This article shows how to run a 5S audit, roll out the system in 90 days and keep it going.
What a 5S audit is and why do it
A 5S audit is a cyclical, standardised assessment of an area against five pillars: Sort, Set in Order, Shine, Standardize and Sustain. It gives you three things that “walking the floor and looking” cannot: a comparable score over time, a list of concrete actions, and a conversation about the standard instead of opinions.
How to run a 5S audit step by step
- Define the area and the team. Two people audit: the area leader and someone from outside. An outside eye sees what the crew has stopped noticing.
- Prepare the audit card. A fixed list of questions, the same every time. Changing questions during the year destroys comparability of results.
- Score on a 0–4 scale. 4 means exemplary, 0 means absent. Mark questions that do not apply to the area as “NA”: they do not count towards the score.
- Take photos and note evidence. A score of “2” without a note of what exactly is wrong does not lead to action.
- Calculate the score. A pillar score is the sum of points divided by the maximum. The overall score is the average of the five pillars.
- Hold a debrief on the spot. Ten minutes with the team: what is good, what to improve, who does it and by when.
- Enter the actions in the plan. Each with an owner and a deadline. Without this, an audit is just an inspection.
Example: pillar 1S Sort
| No. | Audit question |
|---|---|
| 1.1 | There are no items in the area that are not needed for current work. |
| 1.2 | Items of unclear purpose carry a red tag with a decision deadline. |
| 1.3 | The quarantine zone is marked, labelled and emptied regularly. |
| 1.4 | Materials and semi-finished goods are in the necessary quantities (min/max). |
| 1.5 | Damaged tools are removed or clearly marked. |
| 1.6 | Documents and instructions at the workstation are up to date. |
| 1.7 | Personal items are only in designated places. |
| 1.8 | There are no hidden stockpiles in cabinets and drawers. |
The full list of 40 questions, with a description of what to check and what a “4” looks like, is in the kit below.
5S Implementation Kit to download (free)
An Excel tool with a results dashboard, a 23-page guide and A4/A3 forms. No registration, no email.
How to implement 5S in 90 days
Days 1–30: foundation
Choose one pilot area, not the whole plant. Run a zero audit, appoint a 5S leader, run a sorting action with red tags and set up a quarantine zone. Take “before” photos.
Days 31–60: system
Define locations (tool shadows, floor markings, min/max levels), set a cleaning and inspection plan, and hang standard photos at the workstations. First follow-up audit after three weeks.
Days 61–90: sustaining
Introduce a short daily check, a weekly review of the action plan and a monthly audit. Post the results on a board. Only now expand to further areas.
How to control and sustain the result
- Target and warning threshold. E.g. target 80%, threshold 60%. Below the threshold an area gets a recovery plan.
- Trend, not a single result. A drop of a few points in two consecutive audits is a signal that the standard is loosening.
- Action plan with deadlines. Overdue = escalation to the area manager.
- Gemba with management. Having supervisors on the shop floor is the best motivator. The following helps: Gemba Walk checklist.
- Root cause analysis. When a problem keeps coming back, use 5 Why analysis.
The most common mistakes
- An audit “just for the paperwork”, with no actions after it.
- Starting too wide: the whole plant at once.
- No area owner and no deadlines.
- Changing the scoring criteria from audit to audit.
- Results seen only by management, not by the crew.
You can run a quick, one-off test online: 5S audit checklist.
Need a tool made to measure?
I can prepare a custom tool or kit tailored to your plant: your own questions, areas and logo, a sheet for a specific process. Just get in touch.
More ready-made tools: Templates.